SMED Checklist: Free Changeover Template for Faster Setups
Free SMED checklist for faster changeovers: before, during and after the stop, plus an internal/external analysis sheet. With fill-in guide and example.
Short answer
A SMED checklist makes sure everything needed for a changeover is ready before the machine stops, and that each changeover follows the same sequence. SMED (Single-Minute Exchange of Die) separates internal work, done while the machine is stopped, from external work, done while it runs. This free SMED checklist covers both, plus an analysis sheet.

Why do changeovers take longer than planned?
- The operator walks away to find tools, parts or the right settings.
- Each shift changes over in a different order.
- The first products after the changeover are scrap because of trial-and-error adjustments.
- Nobody measures the real changeover time, so nobody improves it.
What is SMED and when do you use this checklist?
SMED is a lean method developed by Shigeo Shingo to cut changeover time. Its steps: record the current changeover, separate internal and external work, convert internal to external, streamline the remaining internal work, and standardize. Use the analysis sheet once per machine to improve the changeover. Use the checklist at every changeover to keep the gains. The full method is in our SMED guide.
Part 1: SMED analysis sheet
| # | Activity | Time (min) | Internal / External | Can it become external? | Improvement idea |
|---|---|---|---|---|---|
| 1 | I / E | ||||
| 2 | I / E | ||||
| 3 | I / E | ||||
| 4 | I / E | ||||
| 5 | I / E | ||||
| Total internal time |
Part 2: Changeover checklist
Header: Machine ______ · From product ______ → To product ______ · Operator ______ · Date ______
Before the stop (external, machine still running)
- Next order, product specification and settings sheet ready
- Tools, dies or change parts at the machine, cleaned and checked
- Materials, packaging and labels for the next order staged
- Gauges and first-article inspection form ready
- Preheating or presetting of tooling done, where applicable
- Changeover team and team leader informed of start time
During the stop (internal)
| # | Step | Standard | Time | Done |
|---|---|---|---|---|
| 1 | Stop machine, make safe (lockout if required) | Per LOTO procedure | [ ] | |
| 2 | Remove remaining product and materials of previous order | Line empty | [ ] | |
| 3 | Remove old tooling / change parts | Quick-release clamps | [ ] | |
| 4 | Clean contact areas | Per cleaning standard | [ ] | |
| 5 | Fit new tooling with locating pins | No adjustment needed | [ ] | |
| 6 | Load settings / recipe | Settings sheet | [ ] | |
| 7 | Remove lock, start machine | [ ] |
After the stop (external)
- First article produced and approved (form no. ______)
- Old tooling cleaned, inspected and returned to storage
- Changeover time recorded: machine stop ____ → first good product ____ = ____ min
- Problems and improvement ideas noted
How do you fill in the checklist?
- 1Analysis sheet. film or time one full changeover. List every activity, however small.
- 2Internal / External. ask for each activity "must the machine be stopped for this?" If not, it is external.
- 3Before the stop. this is where most gains are. Make it a fixed trigger, e.g. 30 minutes before end of order.
- 4During the stop. keep the internal steps in a fixed order. Add your machine-specific standards.
- 5Changeover time. measure from last good product to first good product at full speed.
Example (blister line, product A → B)
| Activity | Before | After SMED |
|---|---|---|
| Fetch forming tools from storage | 12 min internal | External |
| Find settings | 8 min internal | Recipe on HMI, 1 min |
| Adjust guides by trial | 15 min internal | Fixed stops, 4 min |
Results depend on the machine and are measured during the pilot.
From paper to digital with Actarion
- AR guidance: each internal step appears on the machine, in the same order, every shift.
- Built-in timing: every step is time-stamped, so you see where changeover time goes.
- Fewer start-up rejects: settings and checks are confirmed in the instruction, not from memory.
- Continuous improvement: analyze step times across shifts and update the instruction centrally.
See the changeover and SMED use case.
Frequently asked questions
Internal setup can only be done when the machine is stopped. External setup can be done while it is running.
From the last good product of the previous order to the first good product of the next order at normal speed.
"Single-minute" means a single digit of minutes. It is a target; any reduction in internal time counts.
Operators, a maintenance technician and a team leader. The people who do the changeover know where the time goes.